Home / Case Studies / Turner Engineering Relocation
Case Study · Industrial · Relocation IT · Western Australia

Turner Engineering moved into a larger operational facility with IT ready before the first day

Turner Engineering relocated from a smaller office into a larger office-warehouse facility in Western Australia. The move could not interrupt customer phone lines, sales-engineer order intake, warehouse pick-and-pack workflows or the field-facing team supporting mechanical-services customers.

Inlight IT delivered the relocation IT scope across site survey, cabling coordination, comms infrastructure, internet, firewall, switching, warehouse Wi-Fi, telephony, endpoints, server relocation and day-one floor support. The new facility was treated as a live operating environment before users arrived, not as a build still in progress.

OFFICE WINGNETWORKWAREHOUSE WI-FI RELOCATION SEQUENCE SURVEYNETWORKCUTOVERWI-FI COVERAGE TURNER / MECHANICAL SERVICES SUPPLY / RELOCATION CONTINUITY FIRST / THEN CAPACITY
Engagement at a glance

Turner Engineering — office & warehouse relocation IT

An operational facility move with sales, warehouse and field operations tied to one IT cutover.

Client
Turner Engineering
Industry
Mechanical-services supply (HVAC products)
Location
Western Australia
Starting point
Relocating from a smaller office into a larger office-warehouse facility
Environment
Office users, warehouse pick-and-pack workflows, field-facing sales engineers and customer-facing phone numbers tied to one IT cutover
Engagement type
End-to-end relocation IT — survey, cabling, comms, internet, firewall, switching, warehouse Wi-Fi, telephony, endpoints, server relocation and day-one support
Outcome
A larger facility online from day one with continuity protected, on a network designed for warehouse operations
Key project stats

An operational facility move, not a simple office move

4
practical workstreams

The project was structured into four practical workstreams, each reducing cutover risk before move weekend.

1
IT cutover

Office users, warehouse workflows, field-facing sales engineers, customer-facing numbers and stock movement were all tied to the same IT cutover.

3
user groups supported

Office, warehouse and field users readied for day one with endpoints, access and floor support.

Day 1
operationally ready

The new facility was treated as a live operating environment before users arrived, not as a build still in progress.

Operating context

The move had to protect sales, warehouse and field operations at the same time

The IT risk was not limited to whether desks had network access on Monday morning.

The relocation touched customer calls, stock enquiries, order processing, warehouse picking, dispatch documentation, remote access and the systems used by sales engineers in the field.

The larger facility also changed the physical shape of the environment, requiring deliberate network design rather than a like-for-like copy of the previous site.

Why this work mattered

This was an operational facility move, not a simple office move

Turner Engineering supplies HVAC products to the mechanical-services industry; its customers rely on timely product availability, accurate stock information, working phone lines and responsive sales support. Inlight IT structured the project around continuity first, then capacity.

01

Everything was tied to one IT cutover

Office users, warehouse workflows, field-facing sales engineers, customer-facing numbers and stock movement were all tied to the same IT cutover.

02

Customer phone lines could not be interrupted

The move could not interrupt customer phone lines, sales-engineer order intake or the field-facing team supporting mechanical-services customers.

03

Warehouse workflows were part of the risk

The relocation touched stock enquiries, order processing, warehouse picking and dispatch documentation — pick-and-pack workflows had to keep moving.

04

The larger facility changed the IT requirement

Network coverage was not just for desks and meeting rooms; it had to support warehouse movement, stock handling and field-facing workflows across the new footprint.

05

The new site needed deliberate network design

The larger facility changed the physical shape of the environment, requiring deliberate network design rather than a like-for-like copy of the previous site.

What Inlight IT delivered

A relocation IT programme built around continuity, readiness and the larger facility

The project was structured into four practical workstreams, with the move weekend run as a controlled cutover. Each reduced cutover risk before move weekend and made sure the new facility was operationally ready before staff arrived.

01

The new facility was specified at the physical-infrastructure level before relocation

Site survey and cabling coordination handled the comms and physical infrastructure ahead of the move.

Included
Site surveyCabling coordinationComms infrastructurePhysical-infrastructure specificationAhead of the move
02

The network was designed for warehouse operations, not only office connectivity

Switching and warehouse Wi-Fi were designed for the larger footprint, not copied from the old site.

Included
Internet and firewallSwitchingWarehouse Wi-FiLarger-footprint coverageWarehouse movementStock handling
03

Trade-facing numbers stayed operational through the relocation window

Telephony was managed so customer-facing numbers kept working across the move.

Included
Telephony cutoverCustomer-facing numbersPorting ahead of cutoverOrder intake protectedRelocation-window continuity
04

Office, warehouse and field users had practical day-one support

Endpoints, server relocation and floor support readied office, warehouse and field users for day one.

Included
EndpointsServer relocationDay-one floor supportOffice usersWarehouse usersField-facing team
05

The move weekend was run as a controlled cutover, not a build

The work that could be surveyed, ordered, configured, ported, tested and validated ahead of time was removed from the cutover window wherever possible, so the weekend was a controlled switch rather than a build.

Included
Pre-move validationOrdering and configuration aheadPorting before the weekendTesting ahead of cutoverControlled switchReduced move-weekend risk
Delivery approach

From site survey to a controlled cutover and a working day one

Select a stage to trace how the move weekend became a controlled cutover rather than a build.

Market context

The move weekend was treated as cutover, not the build phase

A high-quality relocation does not rely on heroic work during the final weekend. The work that can be surveyed, ordered, configured, ported, tested and validated ahead of time was removed from the cutover window wherever possible, so the weekend was a controlled switch rather than a build.

4

Four practical workstreams, each reducing cutover risk before move weekend.

1

One IT cutover tying together office users, warehouse workflows, field-facing sales engineers and customer-facing numbers.

3

Office, warehouse and field users all had working endpoints, access and visible support when the facility opened.

Day 1

The new facility was treated as a live operating environment before users arrived — online from day one.

Turner Engineering relocation engagementInlight IT delivery record
What changed for the client

A larger facility came online with continuity protected and the IT foundation reset

The relocation was structured around continuity first, then capacity. The larger facility came online with customer contact, warehouse workflows and field operations protected, on a network designed for the new footprint.

O·01

Customer contact stayed live

Trade-facing phone numbers and customer communication remained available through the move.

O·02

Warehouse workflows were protected

Pick-and-pack activity, stock enquiries and dispatch documentation were treated as part of the cutover, not afterthoughts.

O·03

The network matched the new facility

Switching and warehouse Wi-Fi were designed for the larger office-warehouse footprint.

O·04

Move-weekend risk was reduced

Survey, ordering, configuration, porting and validation were handled before cutover wherever possible.

O·05

Users had practical day-one support

Office, warehouse and field users had working endpoints, access and visible support when the facility opened.

O·06

The new site became easier to operate

The relocation reset the environment into a cleaner, more supportable model.

Net position

A high-quality relocation does not rely on heroic work during the final weekend — the new site was treated as a production environment before the business depended on it.

Project outcomes

The new site was treated as a production environment before people moved in

Outcome 01

Continuity first

Calls, warehouse and field operations protected.

Outcome 02

Designed for the warehouse

Network built for the larger footprint.

Outcome 03

Numbers stayed up

Trade-facing telephony maintained through the move.

Outcome 04

Validated ahead

Work moved out of the cutover weekend.

Outcome 05

Day-one support

Office, warehouse and field users supported on the floor.

Outcome 06

Foundation reset

A cleaner, more supportable environment at the new site.

Technology and service scope

The scope ran from site survey to day-one floor support

Site and physical infrastructure

6
  • Site survey
  • Cabling coordination
  • Comms infrastructure
  • Physical-infrastructure specification
  • Relocation scoping alongside fit-out
  • Larger-footprint planning

Network and connectivity

6
  • Internet and firewall
  • Switching
  • Warehouse Wi-Fi
  • Warehouse coverage
  • Remote access
  • Network design for the footprint

Telephony and continuity

6
  • Telephony cutover
  • Customer-facing numbers
  • Porting ahead of cutover
  • Trade-facing continuity
  • Order-intake protection
  • Move-weekend cutover

Endpoints and day-one readiness

6
  • Endpoints
  • Server relocation
  • Day-one floor support
  • Office users
  • Warehouse users
  • Field-facing team
Practical next step

Relocating an office, warehouse or operational facility?

We scope relocation IT alongside the fit-out so the site is ready before move-in.

Discuss your relocation IT